Project Details
Project: Anderson Road-Keslinger Road to IL Rte 38 New Construction
Date Posted: 3/8/2012
Limits: Keslinger Road to IL Rte 38 in Elburn Illinois
Service Type: Phase III
Project Scope: Reconstruction and new construction of Anderson Road with bridge at UPRR
Firms Contacted: 140
SOIs Received: 26
Short Listed Firms:
STV
Bollinger, Lach and Assoc
HR Green
STV-193
Bollinger,Lach and Assoc-198
HR Green-202
Firm Selected: HR Green
SOI Document(s): anderson FTP sites
Request statement of interest_Anderson Road-Keslinger to IL Rte 38-3-9-2012